Floor screed drying times

Below is a table for our observed average foot traffic and drying times for these products
	Quality Pex AL Pex barrier pipe 	Quality RWC A rated pump kit 	Quality stainless steel manifold 	Quality installation of UFH 	Quality floor screeding service ADH Flooring Ltd Underfloor Heating & Floor Screeding Contractors  Traditional screed (Premixed 1:4) 24 - 48 hours 1mm per day 20 - 25N Mapei Topcem (1:6) 6 - 24 hours 3 days 27 - 30N Fast - set screed (1:5) 1 -2 hours 25 - 75mm per day 22 - 27N K-screed (1:4) 6 - 12 hours 25mm per week 30N+ Tarmac Truscreed (1:4) 24 - 48 hours 25mm per week 30N+ Gyvlon / Supaflo etc (flowing screeds) 6 - 48 hours 1mm per day 25 - 27N Granolithic screeds 12 - 28 hours 2mm per day 40N+ Tarmac Cemscreed5 (SB) 6 - 24 hours 5 days (2 days) 30N+

Typical ground floor screed

.